Long-term Major Water
Supply Project Milestone Commitments
The following milestone
commitments are agreed to for the large water supply project:
-
Project description to
PSC--January 15, 2007
-
Preliminary conceptual
design--Sept. 30, 2007 (facility/site layout, plant hydraulic
gradient, process description, design basis)
-
Submit DEIS and all
required environmental permit applications--Sept. 30, 2008
-
Complete pilot plant
studies, if required--Dec. 31, 2009
-
Obtain environmental
permits--Sept. 30, 2010
-
Complete 50%
design--Sept. 30, 2011
-
Begin
construction--May 31, 2013
-
In-service--Dec. 31,
2015
This calendar for providing service is taken from United Water
PSC Agreement 10/06.
|