NYS
Dept. of Environmental Conservation Issues Stop Work Order at Ballpark
Site Due to Environmental Violations
March 11, 2011 After an inspection at the site yesterday,
the NYS DEC found a number of violations and ordered a stop to all
construction activities except for the work necessary to correct the
half dozen violations. This is not the first time violations have
shut down the project.
The following is from the Notice of
Violation sent today to Christopher St. Lawrence, Leonard Jackson
engineering group overseeing the project, and the Town of Ramapo:
"At the time of the inspection,
sediment was discharging from the detention pond into the receiving
water resulting in a contravention of New York State Quality
Standards in the receiving water.
In addition, it appeared that a portion
of the detention pond had been filled in. This was also observed by
Environmental Conservation Officer Nicholas Desotelle on March 5,
2011. At the time of ECO Desotelle's inspection, the pond was being
filled in. This is not in accordance with the Stormwater Pollution
Prevention Plan
The approved phasing plan and
stabilization schedule [are] not being followed. Construction in
phases two, three, and four is occurring simultaneously. This is a
violation of the Environmental Conservation Law."
The list of violations also includes
the following deficiencies:
1. Construction entrances must be
maintained.
2. Silt fence must be maintained.
3. Slope on the outside and inside of the detention pond are failing
and are not properly stabilized.
4. The slope on the west side of the site is failing and is not
properly stabilized.
5. Any areas not under active construction for 14 days must be
stabilized.
The letter orders, "These deficiencies
should be corrected immediately. This department is ordering a stop
to all construction activities. Failure to abide by this Stop Work
Order will result in additional penalties under the Environmental
Conservation Law (up to $37,500 per day per violation)." And the letter ends, "Please submit a copy of the Stormwater Pollution Plan by March 25, 2011."
With recent cost overruns that have
reached $1million a week, it is shocking that this is the quality of
work that is being charged to the taxpayers. Apparently, St.
Lawrence's mad rush to meet deadlines in June has cancelled, in his
mind, the need to observe clean water and other environmental laws.
Work will not be able to continue at
the site until the Stormwater plan is submitted and the violations
are fixed. Then another inspection will be required.
A similar Stop Work Order was issued
against the ballpark project on October 12, 2010.
Michael Castelluccio
Preserve Ramapo
www.PreserveRamapo.org
If you would like to be added to our email list and receive
updates on the articles posted on the site, send your email address
to pr.webmaster@gmail.com
|